IFC 5 Building Progress Report - 27 Feb 2018

The facade work is in progress, with the weather toughness complete up to the fifth floor.

The ground floor is now 80% glazed.

Roof membrane is now complete and the insulation is in progress.

M&E first fix completed on the first and second floors and in progress on the other floors, including the risers and basement.

The blockworks are completed on each floor except the ground floor.

Plasterboard partitions and dry lining are in progress on every floor except the ground floor.

Screed completed in the basement, first & second floor and in progress on the third floor.

Access flooring completed on the second and fourth floor and in progress on the third floor.

The suspended ceiling works have started on the first, second and third floors.

Installation of the roof plant is in progress.

External works (services and kerbs) are in progress including drainage works in Trenton Square.