IFC 5 Building progress report - Nov 2017

We are delighted to provide the bi-monthly building construction update for IFC 5 as of 25 November 2017

  • The metal decking and the reinforced concrete slabs are complete.
  • Fa├žade installation has started; curtain wall is completed on the first floor and in progress on the second floor. Precast concrete cladding installation is in progress at ground floor level.
  • Blockworks in the basement are in progress.
  • M&E first fix has started in the basement, the first floor and the second floor.