IFC 5 Building Progress Report

IFC 5 Construction Progress Report (as of 22 July 2017)

  • Reinforced concrete core walls are in progress
  • The ground floor slab in progress
  • The RC core walls up to the fourth floor are complete
  • The back filling around the basement is in progress

4 week forecast:

  • RC core walls expected to be complete up to the top of the 5th floor and roof level
  • Steel frame erection to commence.