IFC 5 Building progress report - Nov 2017
We are delighted to provide the bi-monthly building construction update for IFC 5 as of 25 November 2017
- The metal decking and the reinforced concrete slabs are complete.
- Façade installation has started; curtain wall is completed on the first floor and in progress on the second floor. Precast concrete cladding installation is in progress at ground floor level.
- Blockworks in the basement are in progress.
- M&E first fix has started in the basement, the first floor and the second floor.