IFC 5 Building progress report - Sep 2017
IFC 5 Construction update as of 22 Sep 2017
Re-inforced concrete structure is complete
The steel frame is in progress with three quarters completed
Water main installed
Back filling around the basement is complete
Propping of ground floor slab has been removed
Off site: the precast concrete cladding elements are nearly complete, fabrication of facade has started (anodising, extrusion).
Photo taken 17 Sep 2017