IFC 5 Construction update for 27 April 2018

Please see below the construction update for IFC 5 - 27 April 2018

  • The M&E fix are in progress on the ground floor, complete on the other floors
  • Plasterboard partitions and dry lining are in progress on 4th and 5th floors, completed on 1st, 2nd and 3rd floor. Final fix has started in the basement and in the 1st & 2nd floor
  • Screed completed with the exception of the ground floor
  • Plastering is in progress on every floor
  • Access flooring are completed with the exception of the ground floor
  • Installation of roof plant is completed, the connections are now in progress
  • External works are in progress and the paving works in Castle Street and colonnade are in progress
  • Precast concrete cladding is near completion, finishes are ongoing