IFC 5 Construction update - 28 May 2018
Construction Progress report for IFC 5 (as of 28 May 2018)
- The first and second office floors are completed and internal snagging and finishes are in progress.
- Fit-out works on the 3rd, 4th and 5th floors are in progress.
- Works on the roof are almost complete and the plant installation is advanced.
- Works on the ground floor are in progress with partitions completed, screed and ceiling works in progress.
- Façade works are completed with the final snagging and cleaning in progress.
- Landscape works are in progress, Castle Street paving is complete and now open to the public.